3.24.15. Hoisting procedure: A hoisting procedure must be developed when a load is handled(1) by more than one hoisting apparatus;
(2) by a hoisting apparatus other than a crane;
(3) on a pallet by a hoisting apparatus other than a fork lift truck.
Where a hoisting apparatus is anchored to an existing structure, the anchor point and its working load limit must be specified in the hoisting procedure.